Q: Deschutes County has a tremendous number of permits not finaled and thus expired. What is the allowable length of time to call in a final inspection when job is complete?

A: Three days as per OAR 918-271-0010(1). Please see ORS 479.560 and 479.570 also. It is the responsibility of the electrical contractor who pulled the permits to make the call to the jurisdiction for inspection. Good communication between the general contractor and electrical contractor is advised prior to requesting an inspection.